Catalog No. SY-PKG-LPT-DUAL
Interconnect LPT dual-unit package
N+1 / dual-feed interconnect package. Two tanks, matched %Z band, separate FAT close per serial.
26-40 weeks ARO · Target, subject to confirmation.
- IEEE C57
- IEC
- BABA interest
- Interconnect ready
- ISO 9001
- UL
Compliance targets for the quotation. Exact standard parts are confirmed on the RFQ; badges are never presented as live factory certificates.
Core ratings
Nameplate band
2 x 250-300 MVA · 345 / 34.5 / 138 kV · 60 Hz
Listing lead time
26-40 weeks ARO. Target, subject to confirmation.
Market lead-time signal
WoodMac survey via ACP (Q2 2025): large/HV power TF avg ~128 weeks - survey/IR planning signal, not a Switchyard Supply quote
Working capital
Interest can be flagged on the quote form. Partner-reviewed, subject to underwriting.
Why yards buy pairs
An N+1 or dual-feed interconnect yard keeps a campus energized through a transformer outage, planned or not. The second tank is insurance priced in copper and steel, and for a data-center campus the outage math usually justifies it. The package exists so both tanks are specified, bid, and evidenced as one coherent purchase instead of two drifting ones.
Matched %Z across two factories
The package spec states one impedance band both tanks must hit. When both units come from one OEM this is routine. When the yard dual-sources across two OEMs, the band plus its tolerance becomes the central spec line, and FAT test reports are the proof. A pair outside the band load-shares badly and gives back the redundancy the yard paid for.
Staggered delivery and separate evidence
Two tanks rarely ship together. Plan the haul, receive crew, and energization sequence for staggered arrivals, and close FAT, transport records, and verified receive per serial. Deposit and progress-payment interest, when flagged, is reviewed against each serial by a licensed working-capital partner. A package discount claim is not part of this listing, and neither is a guaranteed pair delivery date.
Deep specifications
- Impedance band
- Indicative 8-12% Z matched band across 2x units for N+1 / dual-feed; confirm before dual-OEM award
- BIL class
- Indicative 345 kV HV BIL + MV (34.5 or 138 kV) per one-line - confirm per RFQ
- Cooling
- ONAF matched stages across dual units preferred. Confirm ODAF if EHV adjacent.
- Standards
- IEEE C57 + IEC 60076. Package docs include dual-source switch CO playbook when pursue path changes.
- Bushings
- Package requires bushing BOM parity plan across dual units. HV bushing LT co-gate risk on 345 kV class.
- FAT protocol
- Indicative - sequential or paired FAT; each unit closes its own fat_passed. Package critical path = slower unit.
Dual-source OEM paths
- Hyosung HICO Memphis (+ KR) - pursue-order path
- Siemens Energy (Charlotte NC LPT localization) - pursue-order path
Documentation pack
Delivered against the order evidence spine, per line item.
- nameplate / rating plate x2
- FAT protocol + certificate x2
- %Z matched band sheet
- oil type + processing procedure
- bushing BOM + spare kit plan (dual)
- heavy-haul / permit plan (dual wave)
- serial registry + as-built pack x2
- Incoterms / title-transfer register
- dual-source switch CO playbook