Campus BTM GSU - 250 MVA · 345/18 kV
Mid-size generator step-up class for a single large gen block stepping up to a 345 kV campus collector.
26-40 weeks ARO · Target, subject to confirmation.
- IEEE C57
- IEC
- BABA interest
- Interconnect ready
- ISO 9001
- UL
Compliance targets for the quotation. Exact standard parts are confirmed on the RFQ; badges are never presented as live factory certificates.
Core ratings
Nameplate band
250 MVA · 345 / 18 kV · 60 Hz
Listing lead time
26-40 weeks ARO. Target, subject to confirmation.
Market lead-time signal
WoodMac survey via ACP (Q2 2025): GSU avg ~143.4 weeks - survey/IR planning signal, not a Switchyard Supply quote
Working capital
Interest can be flagged on the quote form. Partner-reviewed, subject to underwriting.
Where this class sits on a one-line
A 250 MVA, 345/18 kV GSU steps one mid-size generation block up to a 345 kV collector or interconnect. It is the workhorse shape when a campus phases generation in blocks instead of building one very large unit, because a smaller tank eases transport, spares strategy, and outage exposure.
Two units of this class can also back a dual-block layout where each gen block gets its own step-up path. That layout keeps a single transformer failure from stranding the whole behind-the-meter plant, at the cost of more yard space and more bushings on order.
Spec fields that belong on the RFQ
Lock MVA per cooling stage, the 345/18 kV pair, 60 Hz, BIL from the yard coordination study, and the IEEE C57 or IEC 60076 standards path. Give %Z as a band when two OEM channels will bid, and note whether the generator excitation system handles regulation or the study requires an OLTC.
Name the docs pack in the RFQ: nameplate and rating plate, FAT protocol and certificate, an impedance record for any dual-source interchange case, the heavy-haul permit plan, and the serial registry entry with as-built evidence. Asking for the pack up front avoids a scramble at receive.
Dual-source and schedule risk
This class has more plausible OEM paths than the largest shapes, which makes it a good candidate for dual-source pursue-order work. Pursue paths are discovery, and they never stand in for a buyer-approved vendor list. If dual-source is off the table, the quotation still proceeds on a single channel.
Lead-time planning still applies. Public analyses from 2024 through 2026 describe multi-year purchase-to-receipt windows for large power transformers, so a 250 MVA GSU belongs in procurement at the same time as the interconnect request, well before the building schedule firms up.
Quotation and working capital
Request a quotation with the field list above and a needed-by date. Supplier deposit and progress-payment interest can be flagged on the same form for review by a licensed working-capital partner. Switchyard Supply is not the lender, and flagging interest never changes the OEM production schedule.